Construction Alerts

Updated April 09, 2014


Date: 3/20/14

Location: Cole Street

Type of Work:  Newnan Utilities' crews and contractors are on Cole Street replacing an old galvanized water line.

Impact to Customers: There will be minimal impact to the customer. The work is scheduled to be completed in 14 business days.


Date: 4/3/14

Location: East Broad Street Area

Type of Work: Newnan Utilities Construction Crew is scheduled to start work on installing new electric wire for the Express circuit on April 14th. The work area will be on East Broad in front of the two stations and a small portion of Roberts Road from East Broad to East Washington Street.

Impact to the Customers: There will be minimal impact to the customer. The duration of work will not exceed 45 days or no later than May 29th.


Date: 4/8/14

Location: Herring Road  Area (Shenandoah Substation)

Type of Work: Newnan Utilities and its contractors are in the process of intalling underground electric wire from our Shenandoah Substation to the new Niagara building site. Work will be on Dart Road to Herring Road and then  KMart Drive.

Impact to the Customers: There will be minimal impact to the customer.  We estimate the work to take appoximatly 30 days to complete.